Hauptverwaltung der Archimedes FM GmbH2017-09-20T15:31:02+02:00

Project Description

Start-up of the Hauptverwaltung der Archimedes Facility-Management GmbH

With the highly efficient Building E3 the Archimedes FM GmbH moved its location from Bad Oeynhausen to Herford since May 2014. A big part of the cooling energy for the innovative Office Building is produced by earth probes or provided by a CHP Power Station with adsorption coldness and used efficiently by means of concrete core activation. The major part of the required power is generated directly at the location.

Project E3-Building
Location Herford
Successes
  • Assistance of commissioning and operating monitoring
  • Malfunctions were shortly identified and eliminated during the commissioning.
Building Equipment Passive House Norm, Wood Pellet Boiler, de-central ventilating devices
Data Points 250

„We have developed an innovative energy concept for the E3-Building. It was important for us as planning specialist of TGA that the complex Installation Engineering functions really well in operating. Therefore, we specified the relevant functions of the Building to the synavision Test Bench and checked them in operation. So we could promptly detect and eliminate errors and optimization potentials in operation.“

Claus-Herrmann Ottensmeier, Manager, Ottensmeier Ingenieure