University Hospital of Düsseldorf

Leber- und Infektionszentrum Universitätsklinikum Düsseldorf
Amortisationszeitraum: 7 months
CO2-Einsparung: 78 tons per year
Customer

Project

Liver and Infection Centre

Location

Düsseldorf

Successes

We achieved an annual saving of 21.000,- € for our customer!

Building Equipment
  • 2 District Heating Transfer Stations
  • 1 Chiller
  • 9 Heating and Cooling Circuits
  • 1 Data Buffer
  • 3 All-Seasons Air Conditioning Systems
  • 3 Heat Exchangers
Data Points

143

Zitat

“Thanks to the digital test bench, we were able to determine considerable potential for optimization in the operation of the building technology within just 4 weeks. The effort for us was low – we just emailed planning documents and operational data to synavision. We are happy to recommend synavision and technical monitoring.”

Daniel Gryzik, University Hospital of Düsseldorf